Mumbai–Ahmedabad Bullet Train status: where it stands
By The Hind Times EditorialPublished Last checked
At a glance
The Mumbai–Ahmedabad bullet train is under construction. The 508 km corridor has 12 stations, and 371 km of viaduct was reported complete as of September 2026. The first section is targeted for 15 August 2027, although published statements differ on whether it runs from Surat to Bilimora or Surat to Vapi.
Key facts
| Length | 508 km |
|---|---|
| Stations | 12 |
| Viaduct complete (September 2026) | 371 km |
| First section target | 15 August 2027 |
Timeline
- Sep 2026
371 km of viaduct reported complete - 15 Aug 2027 (target)
First section
Viaduct progress is not open track
A completed viaduct still needs track, power supply, signalling, stations, testing and safety clearance. That is why our progress bar shows no open length yet.