Bridges & Tunnels

Atal Tunnel: Route, Length and Travel Guide for Manali to Lahaul

Short answer

The Atal Tunnel is a 9.02 km highway tunnel under the Rohtang Pass in Himachal Pradesh. It carries the Manali–Leh road between the Kullu valley and Lahaul. Opened on 3 October 2020, it avoids the high pass and needs no separate permit.

By 7 min read

Atal Tunnel entrance gate at Rohtang in the Himachal mountains
On this page
  1. Key takeaways
  2. Atal Tunnel at a glance
  3. Route from Manali to Lahaul
  4. Atal Tunnel temperature and weather
  5. Driving rules inside the tunnel
  6. Safety systems built into the structure
  7. How the tunnel was built
  8. Atal Tunnel or Rohtang Pass?
  9. Winter checklist before you start
  10. Planning a day trip from Manali
  11. Frequently asked questions about the Atal Tunnel
  12. Drive smart through the mountains
  13. Sources

Key takeaways

  • Length: 9.02 km, one tube with two lanes, on NH 3.
  • Opened on 3 October 2020; built under the Border Roads Organisation.
  • The Manali–Keylong trip fell from about 116 km to 71 km.
  • Winter snow can still close approach roads, so check advisories first.

The Atal Tunnel lets travellers pass beneath the Rohtang range instead of climbing over it. Before it opened, snow cut Lahaul off from Manali for months every year. Today the 9.02 km road link keeps that valley far better connected, although mountain weather still sets limits.

So this guide covers the route, length, temperatures, driving rules and safety systems. It also explains when the old pass road still makes sense. Meanwhile, for more structures, visit our bridges and tunnels section or the India infrastructure tracker.

Atal Tunnel at a glance

Detail Information
Length 9.02 km
Location Under the Rohtang Pass, eastern Pir Panjal range
Highway NH 3, Manali–Leh route
Altitude About 3,000 to 3,100 m
Layout Single horseshoe-shaped tube, two lanes
Finished width 10 m including footpaths
Opened 3 October 2020
Permit Not required for the tunnel

See the dated entry on our Atal Tunnel status page.

Route from Manali to Lahaul

First, the southern portal lies roughly 25 km from Manali on the Kullu side. You drive up the valley, enter the tunnel and come out near Sissu in Lahaul. From there, the road continues towards Keylong and Darcha, and onward to Ladakh in the open season.

Comparison (Manali to Keylong) Old route via Gramphu Through the tunnel
Distance About 116 km About 71 km
Typical time in good conditions 5 to 6 hours About 2 hours
Exposure to the high pass Yes Avoided

In short, the saving is about 45 km and several hours. Delays at the portals during holiday weekends can reduce the time gain, so plan for queues in peak season.

Atal Tunnel temperature and weather

Conditions outside the tunnel vary sharply through the year. Published project data give about 25 to 30 °C in May and June, and as low as −30 to −20 °C in December and January. The warmer figure describes summer highs, while the cold figure reflects severe winter conditions in the region.

Season What to expect Drive advice
April to June Mild days, melting snow at higher points Start early to avoid traffic
July to September Monsoon rain, landslide risk on approaches Check road reports before leaving
October to November Clear skies, cold nights Carry warm layers
December to March Snow and ice, possible closures Travel only after authorities allow traffic

So do not judge the road from the weather in Manali town. Higher stretches near the portals can freeze even on a bright day.

What the Atal Tunnel temperature means for your car

Cold affects vehicles as well as people. For example, weak batteries often fail on freezing mornings, and tyre pressure falls as the air cools. So check both before you leave Manali.

Inside the tunnel, conditions are usually steadier than at an open pass. However, the road can change sharply once you exit near Sissu. Sunlight, wind and shade may leave wet patches next to dry ones. As a result, you should brake gently for the first stretch after the portal.

Diesel can thicken in severe cold, while windscreens can mist over. Therefore, use the fuel recommended for the season, test your heater and carry a cloth. If snow is falling, wait for official clearance instead of trusting a short break in the weather.

Driving rules inside the tunnel

Treat the tunnel as a controlled safety zone. The following rules protect everyone:

  1. Follow the posted speed limit. Published figures range from 40 to 80 km/h, so rely on the signs.
  2. Do not stop except in a real emergency.
  3. Do not overtake or change lanes against markings.
  4. Keep headlights on low beam.
  5. Keep a safe gap from the vehicle ahead.
  6. Never step out to take photographs or videos.

Also, cameras monitor traffic, and police can fine violations. Fill fuel and visit a restroom before you reach the portal.

If your vehicle breaks down

Switch on hazard lights and stay calm. Then move as far to the side as safely possible and switch off the engine. Then use the nearest emergency facility or call for help. Follow instructions from tunnel staff, and use the emergency exit route if told to leave.

Safety systems built into the structure

The tunnel was also designed with several layers of protection. An emergency escape passage, about 2.25 m high and 3.6 m wide, runs beneath the main road.

System Purpose
Escape tunnel under the carriageway Lets people leave during fire or an accident
Semi-transverse ventilation Moves fresh air and clears fumes
Pollution sensors Trigger extra fans when air quality drops
Fire hydrants Help crews control a fire quickly
CCTV with monitoring rooms Watches traffic from both ends
Public address system Passes instructions to people inside
Avalanche control works Protect the approach roads

The design capacity is about 3,000 cars and 1,500 trucks a day.

How the tunnel was built

The idea, however, is old. A tunnel across the pass was suggested as early as 1942. Prime Minister Atal Bihari Vajpayee announced the project in June 2000, and the tunnel was later named in his honour. Later, the Border Roads Organisation took charge in May 2002.

An Afcons and Strabag joint venture received the main contract in 2009. Drilling then began on 28 June 2010, and the two ends met in October 2017. Crews used drill-and-blast work with the New Austrian Tunnelling Method rather than a boring machine.

Even so, the ground was difficult. Engineers faced water inflow, weak rock, a 30 m roof fall in 2013 and dozens of avalanche sites. These problems explain why the work took about a decade of tunnelling.

Atal Tunnel or Rohtang Pass?

So choose based on your goal. The tunnel is the practical route to Sissu, Keylong and beyond. The pass road is the scenic climb, but it is seasonal and requires a vehicle permit for many visitors.

  • Choose the tunnel for a faster, lower-risk journey into Lahaul.
  • Choose the pass only when it is open, you hold any required permit and conditions are clear.
  • Combine both on a day loop if the authorities allow and daylight permits.

The tunnel does not by itself guarantee year-round travel to Ladakh. That is because the highway beyond crosses other high passes that close in winter.

Winter checklist before you start

  • Check the latest advisory from Kullu or Lahaul-Spiti police.
  • Confirm that your vehicle may travel; some days are limited to four-wheel drive or local traffic.
  • Carry snow chains only if you know how to fit them.
  • Pack warm clothing, water, snacks and basic medicines.
  • Share your plan with someone, as mobile signal may drop.
  • Return before dark when ice is likely.

Coastal engineering poses very different challenges. Compare it with the Atal Setu sea bridge in Mumbai. Meanwhile, Hyderabad drivers can read about the Nehru Outer Ring Road.

Planning a day trip from Manali

A trip to Sissu through the Atal Tunnel is popular because the drive is short. Still, a simple plan makes it smoother.

Step What to do
The evening before Read the police advisory and weather forecast
Early morning Fill fuel and check tyres, wipers and battery
Before the portal Use a restroom and keep documents handy
In Lahaul Park only in marked places and carry waste back
Afternoon Start the return before light fades

Taxi travellers should confirm whether the fare includes waiting time and any local charges. Meanwhile, self-drivers should note that holiday traffic can build near both ends of the tunnel. If you have a heart or breathing condition, ask a doctor before travelling to high altitude, and turn back if you feel unwell.

Frequently asked questions about the Atal Tunnel

What is the length of the Atal Tunnel?

The tunnel is 9.02 km long.

Where is the tunnel located?

It runs under the Rohtang Pass in Himachal Pradesh, linking the Manali side with the Lahaul valley.

When did it open?

It was inaugurated on 3 October 2020.

What is the speed limit inside the tunnel?

Published figures differ, ranging from 40 to 80 km/h. Obey the signs displayed on the day you travel.

Do I need a permit to use it?

No separate permit is needed for the tunnel. The Rohtang Pass road has its own permit rules.

Is the tunnel open in winter?

It is built for all-weather use, but heavy snow or ice can close the approach roads. Check police advisories first.

How much distance does it save?

The Manali to Keylong journey is about 71 km through the tunnel, compared with about 116 km on the old route.

Drive smart through the mountains

The Atal Tunnel makes the trip to Lahaul shorter and safer, yet it remains a mountain road. Check the weather and police updates, fuel up early and respect every sign inside. Then estimate your trip cost with our fuel cost calculator and leave enough daylight for the return.

Sources

  1. Border Roads Organisation, project agency
  2. Press Information Bureau, Government of India: Atal Tunnel documents
  3. Wikipedia: Atal Tunnel (design, construction and safety details)

Information only. The Hind Times is not affiliated with any government or organisation. See our disclaimer.

A publication byline for our independent infrastructure desk. We name sources, date each status check and correct confirmed errors. We are not affiliated with any government or organisation. Read the methodology.

Project status

  • Atal Tunnel
    Bridges & Tunnels · Himachal Pradesh
    Open
    9.02 of 9.02 km open
    Checked
  • Atal Setu
    Bridges & Tunnels · Mumbai
    Open
    21.8 of 21.8 km open
    Checked